Before you resequence production, make sure the next job can run.
One material shortage can set off a chain of decisions: reconcile the BOM with available stock, confirm the supplier delivery, check production capacity and decide what to run instead. The playbook follows a worked example from the first shortage signal to a documented decision.
- Check whether the full kit is ready, not just what the ERP says is in stock. Compare on-hand with usable stock, reservations, Quality holds and the current BOM revision before you release a work order.
- Trace a shortage from the open PO to the affected work order. Follow WO-1204: 500 units required, 350 on hand, 30 on hold. Size the conditional 180-unit gap before you check reservations, the supplier ETA and the affected production start.
- Decide whether to delay, resequence, split or expedite. See when each option works, and when a changeover, a partial kit, a late receipt or another customer commitment makes it the wrong call.
- Know which confirmation is still missing, and who owns it. Procurement confirms supplier commitments. Quality confirms release timing. Warehouse verifies stock. Planning checks that the alternative order is fully kitted and has capacity.
- Know when to reopen the decision after the schedule changes. Keep the latest confirmed date, the decision owner, the next check and the affected work orders together. A field checklist helps you apply the method to your own planning process.
Keep the spreadsheets that already work. The time goes into reconciling what changed and getting a confirmed decision back to the people running the schedule.
A worked example: the 180-unit gap
Work order WO-1204 needs 500 units of Component A by Monday 08:00. The records disagree on what is available:
| Record | What it shows |
|---|---|
| Work order and BOM | 500 units required. Verify the BOM revision and reservations. |
| Warehouse | 350 units on hand after Friday's count. Confirm pick location and allocations. |
| Quality | 30 units on hold. Don't assume release. |
| Open PO | 250 units outstanding. The ERP expects Monday; the supplier now says Wednesday. |
| Alternate job WO-1301 | Confirm its full kit, routing, labor and machine time before moving it up. |
The gap is 500 required minus (350 on hand minus 30 held), which is 180 units, and only if nothing else is reserved. If 40 usable units are already reserved, the gap is 220. If the 30 held units are released in time, it's 150. The 250-unit PO is not Monday stock.
Four responses to a material shortage
Rule out the options that can't run before you compare their costs. Feasibility comes first, then customer exposure, then capacity, then incremental cost.
| Response | When it's the right call |
|---|---|
| Delay the order | The customer has slack, a recovery slot is reserved, and receiving and Quality can finish before it. |
| Resequence another job | The alternate job is fully kitted, its changeover is approved, and no higher-priority job moves. |
| Split the run | A smaller batch is permitted, partial output can ship, and the second setup is worth it. |
| Expedite the shortfall | A confirmed material-ready time protects a commitment worth more than the full premium. |
The playbook works through the cost of each response, the 10-minute exception review that aligns Procurement, Quality, Warehouse and Operations, and the metrics that show whether shortages are getting easier to resolve.
Questions planners ask
Frequently asked questions
How do you size a material shortage before releasing a work order?
Start from the quantity the work order needs, then subtract only the stock you can use by the start time: on-hand stock minus held lots and units already reserved for other orders. An open purchase order counts only once the material has arrived, passed inspection and reached the line.
Should you delay, resequence, split or expedite when materials arrive late?
Rule out what can't run first. Then compare customer exposure, capacity and incremental cost. Delay works when the customer has slack and a recovery slot is reserved. Resequencing works when the alternate job is fully kitted. Splitting works when a partial batch can ship. Expediting works when the commitment it protects is worth more than the premium.
Who should own each confirmation in a material shortage?
Procurement confirms supplier delivery, Quality confirms when held stock can be released, Warehouse verifies stock and reservations, Planning checks that the alternative order is ready, and Operations approves the capacity change. Each check gets a named owner and a time.
Which metrics show whether production planning is improving?
Material readiness, schedule adherence against the frozen schedule, supplier ETA variance, expedite premium and time-to-decision. Keep removed jobs in the adherence count, or a schedule that drops its hardest jobs looks better than it is.
Do I need to replace Excel or the ERP?
No. Keep the spreadsheets and ERP reports that work. The playbook focuses on how supplier updates, usable stock, production constraints and decisions reach the right people.